View Case Filings for: 2020-00218
Service Type:Water
Filing Date:7/9/2020
Category:Regular
Utilities:
Breathitt County Water District
Electronic Case
Case Nature:
ELECTRONIC APPLICATION OF BREATHITT COUNTY WATER DISTRICT FOR THE ISSUANCE OF A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT A WATER IMPROVEMENTS PROJECT PURSUANT TO THE PROVISIONS OF KRS 278.020 AND 807 KAR 5:001
Case Filings | |
---|---|
Filing | Documents |
11/17/2021 11:12:15 AM
Order Entered: 1. Breathitt District is denied an extension of time through April 5, 2022, to submit an application for a traditional adjustment in rates or an ARF. 2. Breathitt District shall file an application for a traditional adjustment in rates or an ARF as soon as possible. Failure to do so may result in the Commission assessing sanctions to Breathitt District. |
|
11/5/2020 8:08:24 AM
Final Order Entered: 1. Breathitt District is granted a CPCN for the proposed project as submitted. 2. Breathitt District's proposed plan of financing is approved. 3. The proceeds from the grant shall be used only for the purposes specified in Breathitt District's application. 4. Breathitt District is authorized to obtain a grant not to exceed $750,000 from the ARC to fund the proposed project. 5. Breathitt District shall obtain approval from the Commission prior to performing any additional construction not expressly authorized by this Order. 6. Notwithstanding ordering paragraphs 3 and 5, if surplus funds remain after the approved construction has been completed, Breathitt District may use such surplus to construct additional plant facilities, if ARC approves of the use and the additional construction, and it will not result in a change in Breathitt District's rates for service. Breathitt District shall provide written notice of this additional construction in accordance with 807 KAR 5:069, Section 4. 7. Breathitt District shall file with the Commission documentation of the total costs of this project, including the cost of construction and all other capitalized costs (e.g., engineering, legal, and administrative), within 60 days of the date that construction is substantially completed. |
|
7/29/2020 2:21:51 PM
Breathitt County Water Districts Response to Public Service Commission Staffs Initial Request for Information (with attachments). Dawn Watts Breathitt County Water District |
|
7/20/2020 11:24:20 AM
Data Request |
|
7/13/2020 12:01:41 PM
20200713_PSC No Deficiency Letter.pdf |
|
7/9/2020 2:01:17 PM
Application of the Breathitt County Water District for the Issuance of a certificate of public convenience and necessity to construct a water system improvements project pursuatn to the provisions of KRS 278.020 and 807 KAR 5:001. This application has all Dawn Watts Breathitt County Water District |
|
7/2/2020 11:58:35 AM
20200702_PSC Acknowledgment Letter.pdf |
|
7/2/2020
Breathitt County Water District Notice of Intent to File an Application for a Certificate of Public Convenience and Necessity Using Electronic Filing Procedures |