View Case Filings for: 2016-00216
Service Type:Water
Filing Date:8/24/2016
Category:Regular
Utilities:
North Shelby Water Company
Electronic Case
Case Nature:
ELECTRONIC APPLICATION OF NORTH SHELBY WATER COMPANY FOR A CERTIFICATE OF PUBLIC CONVENIENCE AND NECESSITY TO CONSTRUCT, FINANCE, AND INCREASE RATES PURSUANT TO THE PROVISIONS OF KRS 278.020 AND KRS 278.023
Case Filings | |
---|---|
Filing | Documents |
9/22/2016 11:26:41 AM
Order Entered: North Shelby is granted a CPCN for the proposed construction as set forth in its application. 2. North Shelby's proposed plan of financing is approved. 3. North Shelby is authorized to issue $3,550,000 of its water system revenue bonds maturing over 40 years at an interest rate not exceeding the lower of 3.125 percent per annum or the interest rate in effect at the time of loan closing. 4. The proceeds from the proposed bond issuance shall be used only for the purposes specified in North Shelby's application. 5. North Shelby shall obtain approval from the Commission prior to performing any additional construction not expressly authorized by this Order. 6. Notwithstanding ordering paragraphs 4 and 5, if surplus funds remain after the approved construction has been completed. North Shelby may use such surplus to construct additional plant facilities if RD approves of the use and the additional construction will not result in a change in North Shelby's rates for service. North Shelby shall provide written notice of this additional construction in accordance with 807 KAR 5:069, Section 4. 7. North Shelby shall file with the Commission documentation of the total costs of this project, including the cost of construction and all other capitalized costs |
|
9/16/2016 2:08:15 PM
Correspondence Affidavits of Publication with Tear Sheets Paula McClain North Shelby Water Company |
|
9/12/2016 11:55:27 AM
Supplemental interest rate information Paula McClain North Shelby Water Company |
|
8/31/2016 3:16:54 PM
20160831_PSC No Deficiency Upon Further Review.pdf |
|
8/31/2016 10:45:17 AM
Response to PSC deficiency letter dated August 30, 2016 Paula McClain North Shelby Water Company |
|
8/30/2016 11:00:20 AM
20160830_PSC Deficiency Letter.pdf |
|
8/24/2016 1:07:44 PM
Application for Certificate of Public Convenience and Necessity to Construct, Finance and Increase Rates Paula McClain North Shelby Water Company |
|
6/24/2016 10:36:54 AM
20160624_PSC Acknowledgement Letter.pdf |
|
6/24/2016
North Shelby Water Company Notice of Intent to File Application for a Certificate of Public Convenience and Necessity Using Electronic Filing Procedures |