View Case Filings for: 2014-00292
Service Type:Electric
Filing Date:8/21/2014
Category:Regular
Utilities:
East Kentucky Power Cooperative, Inc. , Farmers R.E.C.C.
Case Nature:
APPLICATION OF EAST KENTUCKY POWER COOPERATIVE, INC. FOR AN ORDER DECLARING THE GLASGOW LANDFILL GAS TO ENERGY PROJECT TO BE AN ORDINARY EXTENSION OF EXISTING SYSTEMS IN THE USUAL COURSE OF BUSINESS AND A JOINT APPLICATION OF FARMERS RURAL ELECTRIC COOPERATIVE CORPORATION AND EAST KENTUCKY POWER COOPERATIVE, INC. FOR APPROVAL TO ENTER INTO A TEN YEAR PURCHASED POWER AGREEMENT AND APPROVAL OF A SPECIAL CONTRACT
Case Filings | |
---|---|
Filing | Documents |
5/15/2015 9:53:22 AM
Letter Dated 05/03/2015 Filing Unredacted April 2, 2015 Order |
|
4/27/2015 11:12:39 AM
Order Entered: Joint Applicants' Petition for Rehearing is denied. |
|
4/9/2015
EKPC and Farmers RECC Joint Petition for Rehearing |
|
4/2/2015 1:56:38 PM
Order Entered: The Glasgow LFGTE Project is properly classified as an ordinary extension of existing systems in the usual course of business, and a CPCN, pursuant to KRS 278.020(1), is not required for its construction. 2. The August 13, 2014 Capacity, Energy and Environmental Attribute Purchase, Sale, and Interconnection Agreement by and between EKPC and Farmers is approved. |
|
3/30/2015 3:05:46 PM
Order Entered: 1. Joint Applicants' Motion for Confidential Treatment is denied as discussed in this Order. 2. Joint Applicants' request for confidential treatment for information contained in information and documentation provided in responses to Staffs First Request, Items 5, 15, 17, and 18.b., is denied. 3. Within seven days of the date of this Order, Joint Applicants shall file revised pages reflecting as unredacted the information that has been denied confidential treatment. 4. The materials denied confidential treatment shall be withheld from public inspection for 20 days from the date of this Order to allow Joint Applicants to seek any remedy afforded by law. |
|
3/30/2015 3:02:58 PM
Order Entered: 1. Joint Applicants' Motion for Confidential Treatment is granted in part and denied in part as discussed in this Order. 2. Joint Applicants' request for confidential treatment for the Joint Application, page 5; Exhibit 1, schedule A; Exhibit 6, page 1, the first sentence; Exhibit 6, pages 2-6, all amounts except EKPC's annual projected Financial Forecast Cost To Members and EKPC's projected Financial Forecast Cost To Members 6-year Average; Exhibit 7, page 2; Exhibit 9, pages 1 and 2; Exhibit 10, pages 2-31; and Exhibit 13, page 6, is denied. 3. Joint Applicants' request for confidential treatment for the amounts listed on Exhibit 6, page 1, the second sentence; and on Exhibit 6, pages 2-6, EKPC's annual projected Financial Forecast Cost To Members and EKPC's projected Financial Forecast Cost To Members 6-year Average, is granted for a period of ten years. 4. Within seven days for the date of this Order, Joint Applicants shall file revised pages reflecting as unredacted the information that has been denied confidential treatment. 5. Use of the materials in question in any Commission proceeding shall be in compliance with 807 KAR 5:001, Section 13(9). 6. Joint Applicants shall inform the Commission if the materials in question become publicly available or no longer qualify for confidential treatment. |
|
3/30/2015 2:57:12 PM
Order Entered: 1. Joint Applicants' Motion for Confidential Treatment is granted in part and denied in part as discussed in this Order. 2. Joint Applicants' request for confidential treatment for responses to Staff's Second Request, Items 2.a. and 2.d., is denied. 3. Joint Applicants' request for confidential treatment of that portion of the response to Staff's Second Request, Item 2.b., containing Farmers' 2015 all-in cost per MWh for power from the Glasgow LFGTE Project is denied. Joint Applicants' request for confidential treatment of that portion of the response to Staff's Second Request, Item 2.b., containing Farmers' 2015 projection of cost per MWh for power from EKPC as projected in EKPC's 2013 Financial Forecast is granted for a period of ten years. 4. Joint Applicants' request for confidential treatment for the CD filed in response to Staff Request, Item 2.e., is granted for a period of ten years. 5. Within seven days for the date of this Order, Joint Applicants shall file revised pages reflecting as unredacted the information that has been denied confidential treatment. 6. Use of the materials in question in any Commission proceeding shall be in compliance with 807 KAR 5:001, Section 13(9). 7. Joint Applicants shall inform the Commission if the materials in question become publicly available or no longer qualify for confidential treatment. - |
|
1/21/2015
East Kentucky Power Coop and Farmers RECC Notice of Submission |
|
12/23/2014
EKPC responses to PSC staff third request for info |
|
12/9/2014 2:50:38 PM
Commission Staff's Third Request for Information to East Kentucky Power Cooperative, Inc. and Farmer's Rural Electric Cooperative Corporation |
|
11/25/2014
EKPC response to PSC staff second request for info dated Nov 10, 14 and motion for confidential treatment |
|
11/10/2014 12:20:47 PM
Commission Staff's Second Request for Information to East Kentucky Power Cooperative Inc. and Farmer's Rural Electric Cooperative Corporation |
|
10/27/2014
EKPC responses to PSC first request for info with petition for confidential treatment |
|
10/9/2014 2:13:20 PM
Commission Staff's First Request for Information to East Kentucky Power Cooperative, Inc. and Farmers Rural Electric Cooperative Corporation |
|
9/19/2014 1:59:57 PM
Order Entered: The procedural schedule set forth in the Appendix attached hereto and incorporated shall be followed. |
|
8/21/2014 11:37:43 AM
Acknowledge Receipt of Filing |
|
8/21/2014
Application of East Kentucky Power Cooperative, Inc. for an Order Declaring the Glasgow Landfill Gas to Energy Project to be an Ordinary Extension of Existing Systems in the Usual Course of Business and a Joint Application of Farmers Rural Electric Cooperative Corporation and East Kentucky Power Cooperative, Inc. for Approval to Enter Into a Ten Year Purchased Power Agreement and Approval of a Special Contract |