View Case Filings for: 2014-00038
Service Type:Gas
Filing Date:2/19/2014
Category:Regular
Utilities:
Kentucky Frontier Gas, LLC
Case Nature:
Charles E. Hardin, Jr.; Complainant; Kentucky Frontier Gas, Defendant
Case Filings | |
---|---|
Filing | Documents |
12/11/2014 2:28:36 PM
Order Entered: The February 19, 2014 complaint was filed by the Complainants is dismissed as satisfied. 2. Within ten days of the date of this Order, Frontier shall provide to the Commission its planned schedule for reconfiguring its compressor station at its connection to the Jefferson system, which will allow Frontier to accept a supply of gas from Jefferson to meet its increased demands. 3. Within ten days of completion of the reconfiguration of its compressor station at its connection to the Jefferson system, Frontier shall notify the Commission. 4. The Executive Director is delegated authority to grant reasonable extensions of time for the filing of any documents required by this Order upon Frontier's showing of good cause for such extension. 5. Any documents filed pursuant to ordering paragraphs 2 and 3 of this Order shall reference the number of this case and shall be retained in the utility's general correspondence file. 6. This matter is closed and shall be removed from the Commission's docket. |
|
10/10/2014
Magoffin County and Kentucky Frontier Gas Memorandum Of Understanding |
|
10/6/2014
Response of Kentucky Frontier Gas, LLC and motion |
|
9/3/2014 9:23:36 AM
Memorandum dated 8/28/2014 for Informal Conference of 8/27/2014; Comments, if any, due within five days of receipt |
|
8/25/2014 2:02:06 PM
Order Entered: informal conference shall be held on August 27, 2014, at 1:00 p.m. Eastern Daylight Time, at the Commission's offices located at 211 Sower Boulevard, Frankfort, Kentucky. Commission Staff shall contact participants by electronic mail to provide details for joining the conference by telephone. |
|
8/18/2014
Charles E. Hardin, Jr. Motion for Informal Conference |
|
7/14/2014
Response to data request of Gregory D Allen |
|
7/14/2014
Kentucky Frontier Gas Responses to PSC's Initial Request for Information |
|
6/30/2014
Kentucky Frontier Gas LLC Data Requests to Complainants |
|
6/20/2014 9:21:18 AM
COMMISSION STAFF'S INITIAL REQUEST FOR INFORMATION TO KENTUCKY FRONTIER GAS, LLC |
|
6/18/2014 3:30:06 PM
Letter Filing Pipeline Safety Branch Incident Reports in the Record |
|
6/3/2014 12:32:37 PM
Order Entered: 1. The procedural schedule set forth in the Appendix, which is attached hereto and incorporated herein, shall be followed. 2. A person who submits a motion to intervene after June 16, 2014, and upon a showing of good cause, is granted full intervention shall accept and abide by the existing procedural schedule. 3. a. Responses to requests for information shall be appropriately bound, tabbed, and indexed and shall include the name of the witness responsible for responding to the questions related to the information provided, with copies to all parties of record and eight copies to the Commission. b. Each response shall be answered under oath or, for representatives of a public or private corporation or a partnership or association or a governmental agency, be accompanied by a signed certification of the preparer or person supervising the preparation of the response on behalf of the entity that the response is true and accurate to the best of that person's knowledge, information, and belief formed after a reasonable inquiry. c. Any party shall make timely amendment to any prior response if it obtains information which indicates that the response was incorrect when made or, though correct when made, is now incorrect in any material respect. |
|
3/10/2014
Kentucky Frontier Gas LLC's Answer of Kentucky Frontier Gas LLC |
|
2/27/2014 2:09:05 PM
Order Entered: Kentucky Frontier is Hereby Ordered to satisfy the matters complained of or file a written answer to the complaint within 10 days of the date of service of this Orders. |
|
2/19/2014
Charles E. Hardin Jr.'s Resubmitted Complaint |
|
2/10/2014 3:04:22 PM
Deficiency letter, information due 2/20/14 |
|
2/5/2014
Charles E. Hardin, Jr. v. Kentucky Frontier Gas |