View Case Filings for: 2013-00266
Service Type:Electric
Filing Date:8/8/2013
Category:Fuel Adjustment Clause
Utilities:
Big Rivers Electric Corporation
Case Nature:
AN EXAMINATION OF THE APPLICATION OF THE FUEL ADJUSTMENT CLAUSE OF BIG RIVERS ELECTRIC CORPORATION FROM NOVEMBER 1, 2012 THROUGH APRIL 30, 2013
Case Filings | |
---|---|
Filing | Documents |
6/18/2019 10:07:58 AM
Order Entered: 1. BREC's August 29, 2013 petition for confidential protection is granted. 2. The designated materials shall not be placed in the public record or made available for public inspection for an indefinite period or until further Orders of this Commission. 3. Use of the designated materials in any Commission proceeding shall be in compliance with 807 KAR 5:001, Section 13(9). 4 . BREC shall inform the Commission if the designated materials become publicly available or no longer qualify for confidential treatment. 5. If a non-party to this proceeding requests to inspect the designated materials granted confidential treatment by this Order and the period during which the materials have been granted confidential treatment has not expired, BREC shall have 30 days from receipt of written notice of the request to demonstrate that the materials still fall within the exclusions from disclosure requirements established in KRS 61.878. If BREC is unable to make such demonstration, the requested materials shall be made available for inspection. Otherwise, the Commission shall deny the request for inspection. 6. The Commission shall not make the designated materials available for inspection for 30 days following an Order finding that the materials no longer qualify for confidential treatment in order to allow BREC to seek a remedy afforded by law. |
|
11/15/2013 9:44:22 AM
Order Entered: The charges and credits billed by Big Rivers through its FAC for the period November 1, 2012 through April 30, 2013, are approved. |
|
10/25/2013
Big Rivers Electric Corporation's Response to PSC Staff's Information Request from the Hearing of October 16, 2013. |
|
10/22/2013 3:39:19 PM
Notice of Filing Hearing Documents |
|
10/10/2013
Big Rivers' response to Staff's Supplemental Information Request |
|
10/8/2013
Big Rivers Electric Corporation Affidavit |
|
9/30/2013 10:30:17 AM
Commission Staff's Supplemental Information Request to Big Rivers |
|
8/29/2013
Big Rivers' responses to Appendix A and a petition for confidential treatment |
|
8/29/2013
Big Rivers' responses to Appendix A and a petition for confidential treatment |
|
8/8/2013 3:08:49 PM
Order Entered: 1.Big Rivers Electric Corporation ("Big Rivers") shall appear in Hearing Room 1 of the Commission’s offices at 211 Sower Boulevard, Frankfort, Kentucky, on October 16, 2013 at 10:00 a.m., Eastern Daylight Time, to submit itself to examination on the application of its Fuel Adjustment Clause (“FAC”) from November 1, 2012 through April 30, 2013. Neither opening statements nor summaries of pre-filed testimony will be permitted. 2. Not less than 7 days and nor more than 21 days prior to the scheduled hearing, Big Rivers shall publish in a newspaper of general circulation in each area in which it serves, notice of the purpose, time, place and date of the scheduled hearing. 3. Big Rivers shall file with the Commission no later than October 11, 2013 proof of publication of its notice for the hearing. 4. The official record of the proceeding shall be by video only. |