Kentucky Public Service Commission


View Case Filings for: 2011-00380


Case Number:2011-00380
Service Type:Gas & Electric
Filing Date:9/20/2011
Category:Regular
Utilities:

Louisville Gas and Electric Company


Case Nature:

Establishment of a Regulatory Asset









Case Filings
FilingDocuments
12/27/2011 9:54:16 AM

Final Order Entered: (1) LG&E is authorized to establish, for accounting purposes, a regulatory asset in the amount of $8.127 million, based on its cots for storm damages and service restoration due to the Windstorm that occurred August 13, 2011. (2) As its total actual Windstorm costs become known, LG&E shall adjust the amount of the asset downward if the total is less than $8.127 million. (3) LG&E shall file the accounting entries it makes to establish and record the regulatory asset authorized herein. LG&E shall file these entries with the Commission no later than January 31, 2012. (4) That amount, if any, of the regulatory asset authorized herein that is to be amortized and recovered in rates shall be determined in LG&E's next rate case based on an examination of its storm preparedness, its storm restoration efforts, and the reasonableness of the costs incurred.


11/16/2011

LG&E's Response to Commission Staff's 110411 Second Request for Info


11/4/2011 11:15:00 AM

Commission Staff's Second Information Request to Louisville Gas and Electric Company


10/28/2011

LG&E's Response to Commission Staff's 1st Request for Info dated 101411


10/14/2011 3:46:02 PM

Commission Staff's First Information Request to Louisville Gas and Electric Company


10/12/2011 2:25:55 PM

Order Entered: (1) The procedural schedule set forth in the Appendix shall be followed in this proceeding. (2) a. Responses shall be appropriately bound. (2) b. Each response shall be answered under oath. (2) c. A party shall make timely amendment to any prior response. (2) d. Any request a party fails to furnish the requested information, that party shall provide a written explanation. (3) Any party filing testimony shall file an original and seven copies with the Commission with copies to all parties of record. (4) LG&E shall give notice of any hearing in accordance with the provision set out in 807 KAR 5:011, Section 8(5). (5) At any public hearing, neither opening statements nor summarization of direct testimony shall be permitted. (6) Any objections or motions relating to discovery or procedural dates shall be filed upon four business days notice. (7) Motions for extension of time shall be made in writing. (8) Nothing contained herein shall prevent the Commission from entering further Orders in this matter.


9/21/2011 8:28:33 AM

Acknowledge Receipt of Filing


9/20/2011

LG&E's Application for an Order Approving the Establishment of a Regulatory Asset