View Case Filings for: 2011-00372
Service Type:Electric
Filing Date:9/2/2011
Category:Regular
Utilities:
Jackson Energy Cooperative Corporation
Case Nature:
Approval to Implement Five New DSM Programs
Case Filings | |
---|---|
Filing | Documents |
2/24/2012 12:55:22 PM
Order Entered: (1) The tariff pages filed by Jackson Energy for the Electric Heat Pump Tune Up Program, Electric Thermal Storage Program, Button Up Weatherization Program and Air Source Heat Pump Program are approved. (2) Jackson Energy shall file, within 20 days of the date of this Order, tariff sheets setting out the tariffs approved herein showing their date of issue and that they were issued by authority of this Order. |
|
11/21/2011 11:08:15 AM
Order Entered: 1. Jackson Energy’s request to allow it to proceed with the untariffed DSM programs during the pendency of this case is granted. 2. The matter is placed in abeyance until further Order of the Commission. |
|
11/21/2011
Jackson Energy's Response to Commission Staff's First Data Request |
|
11/3/2011
Jackson Energy's Motion to Life Suspension of Demand-Side Programs |
|
11/2/2011 3:59:09 PM
Memorandum dated 11/02/11 for Telephonic Informal Conference of 10/31/11; Comments, if any, due within seven days of receipt |
|
10/28/2011 9:59:41 AM
Commission Staff's Notice of Telephonic Informal Conference |
|
10/27/2011
Jackson Energy's Motion For Extension of Time |
|
10/25/2011
Jackson Energy's Motion for Informal Conference |
|
10/10/2011 10:50:36 AM
Commission Staff's First Information Request to Jackson Energy Cooperative Corporation |
|
9/22/2011 10:57:10 AM
Order Entered: Jackson Energy's proposed DSM programs are suspended for a period of five months from the earliest date that the DSM programs are proposed to become effective, or October 2, 2011 up to and including March 1, 2012. |
|
9/2/2011
Jackson Energy Cooperative's Tariff Filing for Approval to Implement Five New DSM Programs |