View Case Filings for: 2011-00233
Service Type:Water
Filing Date:7/1/2011
Category:Regular
Utilities:
Graves County Water District
Case Nature:
APPLICATION OF GRAVES COUNTY WATER DISTRICT FOR APPROVAL OF CONSTRUCTION AND ISSUANCE OF A CERTIFICATE OF CONVENIENCE AND NECESSITY FOR THE PURCHASE AND INSTALLATION OF AUTOMATED METER READING EQUIPMENT
Case Filings | |
---|---|
Filing | Documents |
11/3/2011 1:49:09 PM
Order Entered: (1) Graves District is granted a Certificate to proceed with the proposed purchase of water meters. (2) Graves District shall notify the Commission prior to installing equipment or facilities not authorized by this Order. (3) Any deviation shall be undertaken only with approval of the Commission. (4) None of the meters may be placed in service until they are tested by an entity that the Commission has approved. (5) Within 180 days, Graves District shall file a written plan. (6) Every 90 days, Graves District shall submit a written report to the Commission. (7) Graves District is authorized to enter into an agreement with KIA for a loan in an amount not to exceed $1,000,000 at an interest rate of two percent per annum and payable over a 20-year period. (8) The proceeds of the loan agreement with KIA shall be used only for the lawful purposes specified in Graves District’s application. (9) Within 90 days of this Order, Graves District shall file with the Commission in writing a plan for obtaining the remaining funds. (10) If the final cost approved in this Order exceeds the estimated cost, Graves District shall notify the Commission in writing within 30 days of determining the final cost and shall provide a written explanation for the additional cost. (11) Any documents filed in the future pursuant to this Order shall reference this case number and shall be retained in the utility’s general correspondence file. |
|
11/1/2011 3:05:04 PM
Memorandum dated 11/01/11 for Telephone Conference of 10/13/11; Comments, if any, due within five days of receipt |
|
10/31/2011 2:13:33 PM
Memorandum dated 10/31 for Telephone Conference of 8/01/11; Comments, if any, due within five days of receipt of letter |
|
10/25/2011 10:21:29 AM
Order Entered: (1) Graves District is permitted to deviate from 807 KAR 5:001, Section 11(2)(a). (2) Graves District's application is accepted for filing as of September 28, 2011. (3) Case No. 2011-00390 is consolidated with Case No. 2011-00233. All future pleadings and documents shall be filed in the record of Case No. 2011-00233. |
|
10/13/2011 1:40:06 PM
Commission Staff's Notice of Conference Call |
|
10/13/2011 12:00:26 PM
Letter Requesting Conference Call |
|
10/10/2011 10:10:20 AM
Memorandum dated 10/07/2011 for Telephone Conference of 10/05/2011; Comments, if any, due within five days of receipt |
|
9/22/2011 9:33:36 AM
Letter entering Graves County Water District's Response to Commission Staff inquiry into the record |
|
9/8/2011 9:34:42 AM
Letter to Graves County Water District Requesting Additional Information |
|
7/19/2011
No Deficiency Letter |
|
7/1/2011 2:41:03 PM
Acknowledge Receipt of Filing |
|
7/1/2011
Application of Graves County Water District for Approval of Construction and issuance of a Certificate of Convenience and Necessity for the Purchase and Installation of Automated Meter Reading Equipment |