View Case Filings for: 2010-00504
Service Type:Electric
Filing Date:1/26/2011
Category:Fuel Adjustment Clause
Utilities:
Jackson Energy Cooperative Corporation
Case Nature:
AN EXAMINATION OF THE APPLICATION OF THE FUEL ADJUSTMENT CLAUSE OF JACKSON ENERGY COOPERATIVE CORPORATION FROM NOVEMBER 1, 2008 THROUGH OCTOBER 31, 2010
Case Filings | |
---|---|
Filing | Documents |
5/31/2011 10:33:38 AM
Order Entered: The charges and credits applied through the FAC for the period from November 1, 2008 through October 31, 2010 are approved. 2. shall deduct 6.76 mills per kWh from its base energy rates (as adjusted for line loss) to reflect the transfer (roll-in) of a negative 6.39 mills per kWh of fuel costs by East Kentucky to its base energy rates as approved in 2010- 00491. 3. The rates in the Appendix to this Order are approved for service rendered on and after June 1,2011, the effective date of East Kentucky’s change in rates. 4. Within 20 days of the date of this Order, shall file revised tariff sheets with the Commission setting out the rates approved herein and reflecting that they were approved by this Order. |
|
3/10/2011
Jackson Energy affidavit of mailing of hearing notice |
|
3/4/2011
Jackson Energy Cooperative's Certification |
|
2/28/2011
Jackson Energy's Response to 012611 Order |
|
1/31/2011
Jackson Energy's Affidavit of Compliance per 012611 Order |
|
1/26/2011 1:28:13 PM
Order Entered: (1) A public hearing shall be held on March 22, 2011 at 10:00 a.m. at the Commission's offices in Frankfort, Kentucky. (2) Jackson Energy shall file an affidavit with the Commission no later than 21 days from the date of this Order attesting to its compliance or noncompliance with the requirements of 807 KAR 5:056. (3) All documents filed with the Commission pursuant to 807 KAR 5:056, Section 1 (7) and (9) during the period under review are incorporated by reference into the record of this proceeding. (4) Jackson Energy shall publish notice not less than 7 days or more than 21 days prior to the public hearing in a newspaper of general circulation in its service areas. Jackson Energy shall also file an Affidavit of Publication of Hearing Notice with the Commission no later than March 18, 2011. (5) The official record of the proceeding shall be by video only. (6) Jackson Energy shall file with the Commission no later than 30 days from the date of this Order, the original and 10 copies of the information requested in the Appendix. |