Kentucky Public Service Commission


View Post Case Referenced Correspondence for: 2010-00223


Case Number:2010-00223
Service Type:Electric
Filing Date:10/14/2010
Category:Merchant Plant Applications
Utilities:

Southern Indiana Gas & Electric Co. d/b/a Vectren Energy Delivery of Indiana, Inc.


Electronic Case
Case Nature:

Southern Indiana Gas & Electric Co. d/b/a Vectren Energy Delivery of Indiana, Inc.









Post Case Referenced Correspondence
FilingDocuments
2/15/2013 4:11:47 PM

Revised Final Location Maps Diagrams


Jason Bentley

VEC_Revised_Final_MapsDrawings_20130215.pdf

Corrected Final Maps & Drawings

2/8/2013 3:38:10 PM

Final As-Built Maps and Certificate of Construction


Jason Bentley

VEC_Final_Location-Maps__Certificate_of_Construction_20130208.pdf

VEC Final Maps & Certificate of Construction

12/20/2012 4:36:22 PM

Vectren Energy Delivery of Indiana, Inc. Annual Report


20121220_Vectren Energy_Annual Report.pdf

Vectren Energy_Annual Report

11/2/2012 11:52:19 AM

Corrected Phase 7 and Amended Phase 6 Plans Profiles Cover Letter


jason bentley

VEC_Phase7__AmendedPhase6_Plans_Profiles_CoverLetter_DateCorrected20121102.pdf

Date Corrected Cover Letter for Phase 7 and Amended Phase 6 Plans & Profiles

9/6/2012

Vectren Energy Response to 071112 Request


9/5/2012 6:16:00 PM

Additional Route Maps and Additional Information


jason bentley

VEC_Route_Request_Additional_Information_20120905.pdf

VEC Route Request Additional Information

8/10/2012 1:35:12 PM

VEC Phase 5 Plans and Profiles


Jason Bentley

VEC_Phase5_PlansProfiles_CoverLetter_20120810.pdf

VEC Phase 5 Plans Profiles Cover Letter

8/3/2012 11:36:11 AM

Phase 2 Plans and Profiles


jason bentley

VEC_Phase2_Plans_Profiles_Coverletter_20120803.pdf

VEC Phase 2 Plans Profiles Coverletter

7/16/2012 3:02:07 PM

Phase Four Construction Plans and Profiles and Cover Letter


Jason Bentley

VEC_Phase4_Plans_Profiles_CoverLetter_20120716.pdf

Phase Four Plans and Profiles Cover Letter

7/12/2012 10:09:44 AM

Route Corridor Clarification Letters


Jason Bentley

VEC_Route_Letters_20120711.pdf

Route Clarification Request Letter and Letters of Support

6/12/2012

Vectren Energy Delivery of Indiana Phase 3 Plans and Profiles for Construction


5/23/2012

Jason Bentley Phase 6 Construction Plans and Profiles


20120523_VEC_Phase6_Plans_Profiles_CoverLetter.pdf

VEC_Phase6_Plans_Profiles_CoverLetter

4/18/2012 4:33:36 PM

Plan and Profiles for Phase One of Construction


Jason Bentley

VEC_Phase1_Plans_Profiles_Cover_Letter_20120418.pdf

Phase One Plan & Profiles Cover Letter

RC_phase1_approval_4-5-12.PDF

Phase One Plan and Profiles

3/22/2012 4:53:47 PM

Letter Regarding Construction Phases


Jason Bentley

2/20/2012 9:30:22 AM

Staff Meeting Request


Jason Bentley

12/21/2011 9:58:02 AM

Annual Update and Cover Letter


Jason Bentley

VEC_Annual_Update_2011.pdf

VEC Annual Update 2011

2/7/2011 11:49:02 AM

Vectren letter regarding attorney visit to Offices of Circuit Court Clerk in Henderson and Webster Counties